Thompson week of 2/22

2/26 | comp design | .5 hours | 2.5 total

2/27 | comp design, group meeting | 2 hours | 4.5 total

Thompson week of 2/8

2/8 | meeting with Hodges | 1 hour | 1.75 total

2/9 | meeting with Hinshaw | .25 hours | 2 total

Dickenson week of 2/22

2/25 | Work on detailed outline | 1 | 1.25
2/27 | Work on detailed outline/meet with Client | 1 | 2.25

Monday, February 23, 2009

Laser Week of 2/22 Time Log

2/23 | quick meeting and comp design | .75 hour | 2.0 hours total

2/27 | quick group meeting | .5 hour | 2.5 hours total
wow... been a while.

Wednesday, February 11, 2009

Laser Week of 2/8 Time Log

2/12 | research on video switcher. visited studio and received tutorial on switcher | 1 hour | 1.25 hours total

Monday, February 9, 2009

Jared Laser week of Feb 2 time log

2/4 | research on video switcher. visited studio | .25 hours | .25 hours total

Jim Thompson Week of Feb 2 time log

2/7 | Research | .75 hours | .75 total

David Dickenson Week of Feb 2 Time Log

Date Activity Time Running Total
2-6 research .25 .25 hrs

Rachel Sarah | Week of February 2 | Time log

2/9/09, Client discussion, .5 hours, 30 minutes